For thousands of other reports visit RSC's Mineral Intellingence Map

Alara Resources Ltd.

opaxe

Summary

Project:

Al Hadeetha

Deposit:Al Hadeetha
Location:Oman
Commodities:Copper-Gold
Date:6/28/2018
Report Code:JORC
Report Type:Feasibility Study
Project Stage:Pursuing Resource Increase/Upgrade
Report details:28-6-2018: Alara Resources Ltd. announces a Feasibility Study report for its Al Hadeetha deposit at the Al Hadeetha project. Updated FS results incl. NPV of US $90M (6%), IRR of 34%, 10.4yr LOM at the project. PERTH: Alara Resources Limited (ASX: AUQ) (Al
Resources:(Reserve, Prob.): 9.7Mt @ 0.88% Cu, 0.22g/t Au at the project
CP/QP:[Overall Report]: Atmavireshwar Sthapak (Internal)
ABSTRACT:PERTH: Alara Resources Limited (ASX: AUQ) (Alara or Company) is pleased to report this update to financial projections previously announced for the Al Hadeetha Copper Project1 in Oman. Further to the Al Hadeetha feasibility study findings released 31 March 20162 and revised on 24 January 20173 , this update takes account of current inputs to the financial model, including higher copper prices, indicative weighted average cost of capital, revised capex and opex pricing and tax increases The Al Hadeetha feasibility study concluded a technically feasible and financially robust mining operation. The process plant is designed to process 1,000,000 tonnes of mineralised material per annum. Project life is anticipated to be 10.4 years. Key Project parameters are summarised below